Sofar S.p.a


Sofar S.p.A.

  • Restructuring of the secondary packaging system and the general locker rooms
Location
Trezzano Rosa (MI) – Italy
Client
Sofar S.p.a.
Engineering
2015
Completion
2016
General contractor
SO.CO.TIS. S.p.A.
Gross area intervention
650 m2
Building costs
400.000 Euro

Client

Sofar S.p.A., an Italian reality, produces pharmaceutical products, Nutritional Supplements and high-quality Medical Devices, with which the medical profession and consumers can meet their own needs.

Realization

Restructuring of the secondary packaging room and the general locker rooms of Building 1. Including the realization of mechanical, electrical and interior design. Delivery of air handling units and extractors, water-sanitary system of the new general sanitation services. The project was designed following the hygiene regulations and according to a risk analysis to determine the criticality of departmental flows.